Construction Contract Forms: Complete Guide to Essential Documents 2025
Master construction contract forms with this comprehensive guide. Learn about proposal forms, change orders, lien waivers, and all essential construction documentation.
Proper construction contract forms are the backbone of successful project management. From bid proposals to final lien releases, the right forms protect your business, ensure compliance, and create the documentation trail needed to get paid and avoid disputes.
This guide covers every essential construction form you'll encounter throughout a project lifecycle. Understanding when and how to use each form is critical for contractors, subcontractors, and project owners alike.
Documentation Is Protection
80% of construction disputes could be avoided or quickly resolved with proper documentation. Every form serves a purpose—skipping paperwork might save time today but creates expensive problems tomorrow.
Understanding Construction Contract Forms
Construction contract forms fall into categories based on project phase. Each form type serves specific legal and administrative purposes:
Bidding and proposal documentation
Agreement and bonding forms
Project management documents
Billing and lien documentation
Pre-Contract Forms
These forms are used during the bidding and proposal phase before contract award:
Official form for submitting a bid on a project. Typically provided by the owner or included in bid documents.
Key Elements
- • Base bid amount
- • Alternate pricing
- • Unit prices
- • Bidder certification
Common Attachments
- • Bid bond
- • Subcontractor list
- • Non-collusion affidavit
- • Qualification statement
Surety guarantee that bidder will enter contract if awarded. Typically 5-10% of bid amount.
- Principal (bidder) information
- Surety company information
- Penal sum (bond amount)
- Power of attorney for surety
Detailed form documenting contractor capabilities, experience, and financial capacity. AIA A305 is the industry standard.
- Company history and structure
- Key personnel qualifications
- Project experience and references
- Financial statements and bonding capacity
Contract Agreement Forms
The core contract documents that establish the legal relationship between parties:
Primary contract between owner and general contractor.
- • AIA A101 (Stipulated Sum)
- • AIA A102 (Cost Plus)
- • ConsensusDocs 200
- • Custom owner forms
Contract between GC and subcontractors.
- • AIA A401
- • ConsensusDocs 750
- • AGC Subcontract
- • Contractor-specific forms
Surety guarantee of contract completion.
- • Typically 100% of contract value
- • AIA A312 standard form
- • Required on most public work
- • Protects owner from default
Surety guarantee that subs and suppliers will be paid.
- • Typically 100% of contract value
- • AIA A312 standard form
- • Required on public work (Miller Act)
- • Protects downstream parties
Project Administration Forms
Forms used throughout construction to manage scope, schedule, and changes:
Documents modifications to the original contract scope, schedule, or price.
Required Information
- • Change description
- • Cost impact (add/deduct)
- • Schedule impact (days)
- • Supporting documentation
Standard Forms
- • AIA G701 Change Order
- • AIA G701S Subcontractor CO
- • ConsensusDocs 503
Formal request for clarification on design documents or project requirements.
- Specific question or issue
- Reference to plans/specs
- Suggested resolution
- Response deadline
Transmittal for product data, shop drawings, and samples requiring approval.
- Submittal description and spec section
- Number of copies required
- Review status (approved, revise, rejected)
- Distribution list
Daily documentation of work performed, conditions, and events.
- • Weather conditions
- • Workforce count by trade
- • Work performed today
- • Materials received
- • Equipment on site
- • Visitors and inspections
- • Safety incidents
- • Delays or issues
Payment Forms
Critical forms for billing and protecting payment rights:
Monthly billing form documenting work completed and payment requested. AIA G702/G703 is the industry standard.
G702 Components
- • Original contract sum
- • Approved change orders
- • Work completed to date
- • Retainage calculations
- • Amount due this period
G703 Schedule of Values
- • Line item breakdown
- • Scheduled value per item
- • Previous billings
- • This period's work
- • Percent complete
Releases mechanic's lien rights in exchange for payment. Four types cover different situations:
Conditional Waivers
- • Progress Payment - waives rights for specific payment upon receipt
- • Final Payment - waives all rights upon final payment
Unconditional Waivers
- • Progress Payment - waives rights immediately
- • Final Payment - releases all lien rights
Never sign unconditional waivers until payment is received and cleared.
Notice to owner/GC of work being performed to preserve lien rights. Required in most states.
- Property information
- Claimant identification
- Description of work/materials
- Estimated amount
Project Closeout Forms
Forms required to close out a project and release final payment:
Documents when project is ready for occupancy (AIA G704).
- • Date of substantial completion
- • Punch list items
- • Warranty start date
- • Responsibilities shift
Confirms all work complete including punch list.
- • All punch items completed
- • Final inspection passed
- • All closeout docs submitted
- • Final payment authorized
Surety approval for final payment release.
- • Required before final payment
- • Confirms no claims pending
- • Releases retainage
Compiled manufacturer and contractor warranties.
- • Equipment warranties
- • Material warranties
- • Workmanship guarantees
- • Maintenance requirements
Digital Form Management Tools
Modern construction increasingly relies on digital forms and document management:
Benefits of Digital Forms
- Instant distribution and access
- Automatic calculations
- Electronic signatures
- Audit trails
- Searchable archives
Popular Platforms
- • Procore (comprehensive PM)
- • PlanGrid/Autodesk Build
- • Textura (payment processing)
- • CMiC (enterprise)
- • AIA Contract Documents Online
Form Management Best Practices
Use consistent form versions across projects
Standardize on one document family (AIA or ConsensusDocs) for familiarity.
Keep forms current
Standard forms are updated periodically. Use the latest versions.
Complete all fields
Blank fields create ambiguity. Use "N/A" where not applicable.
Get proper signatures
Ensure signers have authority. Verify corporate authorization.
Maintain organized records
Keep executed originals. Implement consistent filing system.
Frequently Asked Questions
AIA Documents are available at aiacontracts.com. ConsensusDocs at consensusdocs.org. Most forms cost $30-100 each or are available via subscription. Some states have mandatory forms for public work available from state agencies.
Yes, but carefully. Modifications should be made in a separate supplementary conditions document rather than striking language in the base form. Have an attorney review any modifications to ensure they don't create unintended consequences.
Subcontractors typically need: subcontract agreement, schedule of values, change order forms, pay applications, lien waivers, and preliminary notices. The GC usually dictates which forms to use to maintain consistency with the prime contract.
Streamline Your Documentation
ConstructionBids.ai helps contractors find opportunities and manage the bidding process efficiently.
Ready to Find Your Next Contract?
Get instant access to thousands of government construction bids with our AI-powered platform.
Start Free Trial